The grid bridge welding equipment includes:
Vertical wire automatic fabrication unit, welding main, CNC forward cutting mechanism, side cutting mechanisms, positioning platform, front and back cutting mechanism and automatic stacking mechanism.
1.The vertical cloth V-groove is divided into two sets, one can move up and down, one can move horizontally, first, the horizontal moving distance according to the width direction of the grid size data, The V-shaped mouth is aimed at the longitudinal chute.The chute is installed in the order that each longitudinal wire is dropped into the V-shaped slot, then moved behind the welding host.The longitudinal wires are picked up by the up-and-down V-shaped chute and pushed into the host for welding.
2.The vertical cloth V-groove is divided into two sets, one can move up and down, one can move horizontally, first, the horizontal moving distance according to the width direction of the grid size data, The V-shaped mouth is aimed at the longitudinal chute.The chute is installed in the order that each longitudinal wire is dropped into the V-shaped slot, then moved behind the welding host.The longitudinal wires are picked up by the up-and-down V-shaped chute and pushed into the host for welding.
3.Reverse the network agency
The network pulling mechanism uses the servo motor + speed reduction drive mechanism to move back and forth, and the tightening of the network sheets uses the pneumatic tightening mechanism to secure the network pieces on the network pulling apparatus.
4.Border agencies
In order to ensure that the trimming speed is higher than the welding speed, the trimming power adopts a servo motor + anti-impact reducer transmission mechanism. The angle of trimming can be adjusted according to the angle of wire fracture. The trimming mechanism is installed on both sides of the wire frame, and the other two sets are installed on the positioning platform. The welded mesh is positioned, and the trimming mechanism is then horizontally moved to trim.
5.The loading agency
The loading agency uses a dragon gate secured agency. It is equipped with eight pneumatic fingers and is mounted on an aluminum slot for easy adjustment.
Working conditions:
Project |
Working conditions |
External power supply |
Three-phase 380 v50HZ, distance from main control ≤ 50 meters |
Control voltage |
DC24V |
Power supply capacity |
Single Control 100-120KW |
Main transformer |
Maximum pressure drop ≤ 10%, short circuit voltage ≤ 5% |
Single phase area of power line |
Aluminum wire 90mm² or Copper wire 50mm 2 |
Work environment |
Temperature 5 ~ 40 ° C, air relative humidity (20 ° C) ≤ 90% |
Cooling system |
Clean, neutral to slightly alkaline (PH = 7 ~ 8) water, flow rate 1.0m3 / h, inlet temperature 25 ~ 30C, inlet pressure 0.15 ~ 0.3MPa, cooling capacity 6kw. |
Gas Source Requirements |
Working pressure 0.5 ~ 0.6 MPa, flow rate about 60 m3 / h |